NBS Source
I'm a manufacturer

Mother Teresa Catholic College, WA

OVERVIEW

Mother Teresa Catholic College, WA

Location – Baldivis, Perth, Western Australia      

Installation Duration - 3 months

Installation Year – 2019                             

Project Value - $15-20 million

Specifying Architects – Parry and Rosenthal Architects

 

TECHNICAL DETAIL

Installation Type                                             Number

Service penetrations                                     150

Cluster penetrations                                      11

Control joints                                                   700 LM

Concrete slab pours                                       Grid pattern - numerous

Perimeter                                                           500 LM

 

 

BACKGROUND

Mother Teresa Catholic College is a progressive co- educational facility in the fast-growing suburb of Baldivis, 60 kilometres south of Perth in the City of Rockingham.

The school opened in 2013 and in 2018/19 a Stage 3 Capital Development Program called for the construction of junior-secondary class-rooms and associated facilities, playing fields, courts, grounds, and extended parking.

 

REQUIREMENT

The College’s ongoing plans for facility enhancements represents a significant investment and is worth protecting with the most effective pre-construction termite management system.

The College caters for students from pre-kindergarten to Year 12. Chemical termite controls were not an option because of toxicity issues, making a clean and environmentally safe physical termite barrier the correct solution.


APPROACH

A typical WA site, the college’s location is predominantly flat, with sandy soils and substrates. In general, this type of environment poses a high risk for termite attack common to this region of Western Australia.

 

SOLUTION

The main challenge with the installation came from the rammed earth exterior walls. Their natural composition can chip easily, so nailing or sealing the termite barrier onto the wall was not practical.

Our solution was to install Termimesh cold joint /paver trays to the perimeter of the concrete slab edge. These protected the concealed entry point between the slab and wall. They also engaged into the external pavement instead of against the rammed earth wall itself.


BENEFITS

The Termimesh System which comprises of our 725 grade stainless steel mesh, Termiparge bonding cement and high grade stainless steel clamps not only met their strict requirement of no chemicals it will also continue to provide them with reassurance and peace of mind the comes with our market leading Pledge Guarantee. The Pledge Guarantee provides the client with a 10 year guarantee that requires no annual inspections during that initial period. The client then has the option to extend this on an ongoing basis by having an approved annual inspection.

Products featured in this case study

View all products (1)
Termimesh Termite System

Termimesh Termite System

More inspiration from Termimesh

View inspiration
Termimesh - Protecting Historical Landmarks – Norwood Oval Adelaide

Termimesh - Protecting Historical Landmarks – Norwood Oval Adelaide