The Challenge
Failing retaining wall needed to be stabilised and strengthened.
The failing masonry wall, to the rear of Latches Close Social Housing, was braced with timber struts and remained like this for 10 years. The ‘temporary’ buttress was effective for a short time but then the wall began to move. The brick retaining wall had fractured at the corner which was a sign it was slowly inching forward. For fear of the wall’s collapse, the surrounding area was cordoned off with heras fencing. For health and safety reasons, the rear of the social housing was completely ‘out of bounds’.
The wall couldn’t be taken down and replaced because there was a car sales elevated above. The car sales proprietor did not want his land to be affected. Clarion Housing Group contacted Engie to survey the failing wall and propose a solution.
The Solution
Secura Grand was installed under the expert advice of Tobermore’s Civil Engineering Consultants.
Engie had previously worked with Tobermore on other schemes and had experience using their Secura Grand Retaining Wall system. Following consultations with Tobermore’s Civil Engineering Consultants, Engie proposed Secura Grand as a solution to strengthen and stabilise the existing wall.
Rather than replacing the entire wall, the existing wall and its timber buttress was incorporated into the retaining wall designs. This retaining wall project has restored land for the residents and property managers.
Secura Grand | Concrete Segmental Retaining Wall
Copthorne Place - Persimmon Homes
Grey Towers Village Country-Chic Meets Modern Living
Telford College of Arts & Technology - Pinnegar Hayward Design
Queen Elizabeth University Hospital - NHS Greater Glasgow and Clyde
Allscott Meads Primary School
John O’Gaunt Golf Club