OVERVIEW

Abbey Upholstery Factory was badly affected by a fire in April 2021 which burnt

down a large section of the facility. Specwall was used in four phases to help rebuild

the internal dividing walls. The majority of these were 6m tall or higher and more than

700m2 of Specwall was required.


The factory is made up of more than 7,000m2 of floorspace and Specwall was chosen

for the refurbishment for three main reasons.


Firstly, to allow the factory to continue operations, walls that fell in the fire needed to

be sealed up as soon as possible to keep the elements out. Specwall’s fast installation

time and the fact it requires no scaffolding made it the perfect choice to complete this

job quickly. The modular nature of Specwall also meant that it could be built around

existing obstacles with ease.

No featured products in this case study

Contact Specwall SP by clicking the button below to find out which products were used in this case study.

More inspiration from Specwall SP

View inspiration
Lucent

Lucent

Beechwood Avenue

Beechwood Avenue

The Crescent

The Crescent

The Ciel Tower

The Ciel Tower