OVERVIEW
Year: 2019
Architect: Maber
Assembly:
· Walls – APL StrongBak™ with external vertical APL profiled cladding
Size:
· Approx 23,000 m² of StrongBak™ & APL external wall profiles
Special Features:
· StrongBak™ system requested direct from client
· A follow-on project from the new BMW Mini factory in Oxford, which APL supplied as the same construction assembly and area
· Building 23m high
· All materials delivered to site within a 6-7 week period
Building Location:
· Swindon, Wiltshire
Long-span Structural Wall Panel System - APL StrongBak™ - Non-Combustible
Trapezoidal Profile (30mm Deep) Wall System - AP30/35-W - Trapezoidal Profile Cladding System
APL Case Study - StrongBak™ - Ball Corporation – New Bottling Plant
APL Case Study - StrongBak™ - Derry Sports Complex
APL Case Study - AP50HR Half-Round Cladding - Bidfoods, Glasgow
APL Case Study - Aluminium Sinusoidal Roofing & Perforated Cladding - Birmingham Energy Innovation Centre
APL Case Study - StrongBak™ - Ball Corporation – New Bottling Plant
APL Case Study - StrongBak™ - Derry Sports Complex
APL Case Study - AP50HR Half-Round Cladding - Bidfoods, Glasgow
APL Case Study - Aluminium Sinusoidal Roofing & Perforated Cladding - Birmingham Energy Innovation Centre