OVERVIEW
Background
The Injured Jockey Fund (IJF) Oaksey House rehabilitation centre in Lambourn, Berkshire, was opened in 2009 by the IJF Patron, HRH The Princess Royal. Oaksey House provides specialist rehabilitation treatment for physical and neurological injuries, it has a fully equipped gym which includes a state-of-the-art anti-gravity treadmill. The centre has respite accommodation available for those receiving extended treatment and their carers. Educational courses on fitness and nutrition for the general well-being of young and aspiring jockeys are also on offer.
Oaksey House is not only a rehabilitation centre for jockeys, but anyone with physical or neurological injuries. Although the centre was only opened in 2009, it was decided that a refit was required to make improvements to further support the people that pass through its doors. The refit included moving the gym to the first floor and building a hydro pool on the ground floor.
The Challenge
Relocating the gym to the first floor was no easy task, primarily because the building structure was composed of a steel tray and concrete base. To accommodate gym activity, the floor build-up would need to be enhanced to prevent noise and vibrations travelling through the building.
As a charity, the IJF had limited funds to work with, so flooring specialists, Sport & Fitness Flooring, worked with the architect and an independent consultancy to identify an effective solution within the specified budget. Moreover, the floor had to be designed to meet the needs of four distinct areas: a cardiovascular zone, a running track, main gym area and an entrance lobby.
The project was unique because various performance requirements had to be met across the four areas but the floor level needed to be consistent throughout to make it accessible for wheelchair users. Sport & Fitness Flooring consulted CMS Danskin Acoustics – Gym Flooring Division to advise on potential solutions to address this challenge while remaining cost effective.
The Solution
CMS Danskin Acoustics worked with Sport & Fitness Flooring to undertake on-site subjective testing to determine the level of sound reduction and vibration control that would be required. The primary objectives were to prevent vibration travelling into the structure of the building thus resulting in potential structural damage or unwanted noise levels on the ground floor below. Samples of different build ups were provided by CMS Danskin Acoustics on site for testing within a day of the initial request.
“Throughout the planning stages CMS Danskin Acoustics acted as a ‘springboard’ for our ideas. They were extremely helpful in offering their expertise to find solutions to meeting the performance requirements of the floor,” said Darren Wood, Director of Sport & Fitness Flooring.
Sport & Fitness Flooring worked with CMS Danskin Acoustics to identify a way of raising the floor in different areas to meet a consistent 84mm thickness throughout, without having an adverse effect on the acoustic performance of the flooring. CMS Danskin Acoustics developed a bespoke specification for the four key areas, with solutions subsequently presented to the architect and approved for use on the project.
The Result
CMS Danskin Acoustics was able to meet the performance, volume, and diversity of product needed to effectively treat the floor at a competitive price and on budget.
In the main gym area, a high-performance combination of everroll® Multitile (everroll Multitile 27mm) was bonded to Regupol® 40/80 Acoustic Foam and fitted to Regupol® Vibration 300. In the cardiovascular zone, Multitile (everoll Multitile 27mm) was bonded to Regufoam® 270 acoustic PU foam and fitted to ply which was adhered to Regupol® Vibration 300. The track was treated with BOK Sprint track bonded to a everroll® Impact Pad elastic layer, ply build up and Regupol® Vibration 300. Finally, concrete effect Luxury Vinyl Tiles (LVT) were used to create a purpose-built ramp up to the 84mm floor level from the entrance lobby.
On day one of the build schedule, there was a timed delivery of the material. The bespoke order was exactly as specified and allowed installation to begin immediately with no delays. CMS Danskin Acoustics attended Oaksey House to provide expert on-site support and technical guidance on the installation. The project finished a week ahead of schedule, on budget and the flooring met all the performance requirements that were specified. Crucially, a consistent floor level was successfully achieved throughout the gym.
“It’s quite common for suppliers to just sell a material and move on, but CMS Danskin Acoustics deliver a first-class expert and professional service from initial technical involvement, to tracking, delivery, installation and sign off. We regularly work with CMS Danskin Acoustics on various bespoke projects and are always confident in the solutions and expertise provided,” concluded Darren.
Contact CMS Danskin Acoustics by clicking the button below to find out which products were used in this case study.
Sound Absorption Solution for Moneypenny Call Centre HQ
SuperLag Quietslab used at ExxonMobil Oil Refinery
Sound Absorption Solution for CCGT Power Station at Landivisiau in Brittany
Nine Elms Parkside Case Study: Under Screed Acoustic Layer