Manchester Airport – Terminal 2

OVERVIEW

Architect: Pascall + Watson Ltd.

London, UK

Contractor: Laing O’Rourke

Dartford, UK

Installer: EKSPAN

Sheffield. UK


The Project

A £1 billion expansion of Terminal 2 that will be 150 percent larger than the original to boost passenger capacity and provide gate and tarmac space for the largest jets now in operation. The new terminal will feature 32 new shops and food and beverage outlets.


Unique Challenge

Architects were concerned about thermal movement creating a 20mm difference in floor heights across the slabs or sections of the terminal. This would present a trip hazard for pedestrians transiting the terminal, which could potentially be present over weeks or even months during the hottest or coldest times of the year.


Solution Provided

Inpro® product designers created a project-specific “glide plate” floor joint. This custom solution had to move in three directions while simultaneously addressing the rigorous heavy-duty loads encountered in this major transportation hub. The new solution was presented as a 3D-printed prototype model only days after the idea was discussed with the architects. The new system can withstand the extreme movements and the additional loading present in airport concourses, from wheeled luggage up to passenger transport vehicles and maintenance equipment.


The new 300HD system easily accepts the flexible Fireline® 520 fire barrier, which recently passed testing for all the European standards.


Inpro® Products Used

• 300HD Glide Plate floor-joint system

• 811 Series cover plate system

• Fireline® 520 fire barrier

No featured products in this case study

Contact Inpro by clicking the button below to find out which products were used in this case study.

More inspiration from Inpro

View inspiration
European Spallation Source (ESS)

European Spallation Source (ESS)

Istanbul Airport

Istanbul Airport

Wythenshawe Hospital

Wythenshawe Hospital

World Trade Center

World Trade Center