OVERVIEW
Allume received an urgent call from a client facing a critical issue. With only three weeks left until project completion, a review revealed that 10 of the flats were just 1 SAP point short of achieving the targeted EPC A rating. The initial solution considered was installing individual PV systems for each flat, but this proved impractical due to insufficient roof space to accommodate 10 panels. Additionally, there was no suitable space inside the flats to install the necessary PV hardware.
Contact Allume Energy by clicking the button below to find out which products were used in this case study.
How a developer met EPC goals with customised solar allocation for flats
Achieving a building of net-zero flats