OVERVIEW
Technical representatives from F. Ball have provided flooring with a cost-effective alternative to completely removing and replacing a weakened screed as part of a flooring refurbishment at the Aberystwyth Arts Centre, part of Aberystwyth University.
Upon removing old floorcoverings, flooring contractors were faced with an extremely rough screed with weak patches, possibly the result of poor installation or curing techniques, environmental factors or age, that was unsuitable for the application of subfloor preparation products and the installation of floorcoverings. Some weak sections were mechanically removed, leaving about 75mm thickness to be made up. A structural engineer confirmed that the concrete bases were, otherwise, structurally sound. New P5 chipboard was affixed to the wood subfloors with screws and glued at the joins.
It is often necessary to completely remove and replace a weakened screed. However, F. Ball technical representatives called upon to conduct a site assessment were able to recommend a less costly and time-consuming solution to make the surface suitable to receive floorcoverings, including quickly raising the level of floors where sections had been mechanically prepared.
Firstly, any remaining weak spots in the base would need to be removed by mechanical means along with any surface contaminants to create a clean, sound micro-textured finish. Any dust and debris should also be swept away.
Moisture tests indicated subfloor relative humidity (RH) levels in the concrete subfloors were as high as 78%, meaning a moisture management solution would be required. Contractors therefore applied a single coat of Stopgap F77 solvent-free epoxy waterproof surface membrane over the entire area to obtain a continuous barrier against subfloor moisture.
Flooring contractors then used Stopgap 600 Base deep section levelling compound to raise the level of floors where weak patches of screed had been removed.
It was also recommended that the chipboard over the raised access floors was checked to ensure that the surface was clean, secure and undamaged before applying a minimum thickness of 0.2mm of Stopgap Fill and Prime over the entire area.
The whole subfloor area was then capped with a layer of Stopgap 1200 Pro high performance levelling compound to create a perfectly smooth base for the receipt of new floorcoverings.
The final phase of the refurbishment was to install Nora rubber sheet floorcoverings using Styccobond F48 PLUS.
Stopgap F77 - Damp Proof Membrane
Stopgap 1200 - Smoothing Compound
Styccobond F48 Plus - Flooring Adhesive
Stopgap 600 Base - Smoothing Compound
Birmingham City Hospital - Ante-natal clinic gets the right treatment with Styccobond F44
Christ Church Primary School - School hall fit for playtime thanks to F Ball
Christ Church School, Frome - F Ball provides adhesives masterclass at Frome school
Eden Court Theatre - F. Ball products star in Eden Court theatre production
UltraFloor makes homeowners dream come true
UltraFloor gets an 'A' for effort at Derbyshire School
UltraFloor set up home at prestigious housing development
Houses of Parliament - London
London Aquatic Centre - Olympic Pool
DAVID LLOYD LEISURE CLUB
Single Storey House, Fife
Walsall Manor Hospital - Case Study
UltraFloor makes country park renovation a walk in the park
UltraFloor is just what the doctor ordered at Warrington Emergency Department