NBS Source
I'm a manufacturer

Mill Conversion to Apartments - AVRO, Manchester.

OVERVIEW

It’s not everyday you get a phone call from an architect asking for help on a grade 2 listed mill building, but that is what happened to us back in April 2017 when Stephenson Studios contacted us with a problem they were having with floor to ceiling heights on their Brownsfield Mill project in Manchester.

Their design criteria was for the existing 75mm thick timber mill boards to be retained and each of the apartments in the building would have these as an exposed ceiling. The idea was to keep the building as rustic and to retain as much of the original look and feel of the listed mill building as possible. Because of this all of the acoustic (Part E.) and fire Building Regs. (Part B.) requirements would have to be installed above the existing floor.

The drawings we were sent through identified a floor build up, on top of the mill boards, at nearly 300mm thick. This started with a self levelling compound on top of the mill boards, to level them to, and then a timber on timber solution with a final layer of cement particle board prior to the oak flooring being installed.

This thick floor section was causing a problem due to the original oak beams that were in place meaning the floor to ceiling heights weren’t as high as they needed to be. This design was compounded flowing the removal of the bitumen floor covering. When the mill boards were exposed and then levels were taken across each of the floors it was clear that the original design was no longer suitable for the project.

With the age of the building some of the mill boards were beyond repair and each of the floors needed levelling up so the use of self levelling compound and a timber/ cement board solution also became a very expensive solution. We were asked if we could come up with a solution that was able to reduce costs and time and also to be able to achieve the required acoustic and fire requirements for this type of conversion project.

Our initial thoughts on the project was to use timber ferrings, 100mm wide at 600mm centres, to lay our Lewis Deck system onto. This was reducing the number of ferrings by 50% (these were originally at 400mm centres) and it also removed 4 layers of timber/ cement board as well as the self levelling compound from the project. Following a meeting on site however, and after being able to fully talk to the design team and developer about what the Lewis Deck system can do we agreed that we would look at putting the ferring strips at 1400mm centres with the Lewis Deck being laid across at these centres. Rubber granulate acoustic strips would be installed on top of each of the timbers and mineral wool insulation would then be installed between. This would allow more material to be removed from the project but crucially still hit both the acoustic and fire requirements of the project.

A test floor was commissioned, by the acoustic engineer, and built in August 2018 which passed all tests. You can see from the photos below the Lewis Deck laid at 1400mm centres for the middle section of the test with the 15mm thick rubber granulate acoustic strip laid on top of the timber ferrings. These timbers, due to the nature of the mill boards below, had to be installed individually to differing heights.

The first full delivery of Lewis Deck arrived on site at the beginning of June 2019 following on from the steel strengthening works that were being carried out on site.

The deck was quickly installed across the whole first floor in just a couple of days and the first screed pour was scheduled for the following week. The whole floor was poured using an anhydrite screed in just a few hours.

The project continued on and the last main section of floor was poured on 19th December 2019, exactly 6 months after the first of the pours.

This grade 2 listed mill building was a great project to work on. One that gave us a lot of challenges to overcome from the outset and one that helped overcome a number of issues that kept dropping up as the remedial works on the building progressed. We are delighted with the final result.

Developer: Urban Splash

Floor Installer: Trent Construction Services Ltd.


No featured products in this case study

Contact CDI Innovative Construction Materials Ltd by clicking the button below to find out which products were used in this case study.

More inspiration from CDI Innovative Construction Materials Ltd

View inspiration
New house, Perth, Scotland

New house, Perth, Scotland

New Lewis Deck Installation Videos

New Lewis Deck Installation Videos

Op-Deck to the Curly House

Op-Deck to the Curly House

2 Storey Beach Front House, Seadune.

2 Storey Beach Front House, Seadune.