OVERVIEW
A hard-wearing durable levelling screed was required for a major redevelopment project at Victoria Hospital in Kirkcaldy, Fife.
Originally opened in 1967, the facility is one of two main hospitals in the county, serving the town and mid-Fife area.
Extended in 2012, the hospital features an East, West and South and a main tower block, housing an accident and emergency department; maternity unit, an ENT unit, anaesthesia, obstetrics and gynaecology, paediatric surgery, mental health services, infectious diseases and operating theatres.
When complete, the latest expansion to the Edinburgh hospital, representing a £33m investment that was approved in early 2021, will see the hospital gain 140 additional parking spaces in a new parking facility, as well as 3 operating theatres, a supporting inpatient ward and associated outpatient facilities.
Vebro Polymers has provided v-Cem – a rapid-drying, high-strength, shrinkage-compensated screed that can be applied prior to the installation of commercial floor coverings, including carpet, titles, laminate or hard-wearing resin finishes.
Laid at depths between 10.0 mm and 55.0 mm and beyond, v-Cem can be used to form screeds that are bonded, unbonded and floating screed applications, and is suited to use in both internal and external applications — ideal for the in-progress construction site of Victoria Hospital.
The expansion of the hospital has included many phases and trades, each keen to maintain momentum to deliver the finished facility in good time. v-Cem will dry in as little as 4 days to receive resin finishes and other resilient floor coverings.
Contact Vebro Polymers by clicking the button below to find out which products were used in this case study.
REPerformance, Swindon, Wiltshire
329 Edinburgh High Street, Edinburgh, Scotland
P D Hook (Hatcheries), Duns, Scotland
Jedburgh Grammar Campus, Jedburgh, Scottish Borders