NBS Source
I'm a manufacturer
Axter Ltd

Axter Ltd

We are revolutionising the way flat roofs are designed, installed, used and maintained.

+44 (0)1473 724056 Website

Sort by:

Showing 1-28 of 28

Sponsored
Abingdon Primary School

Abingdon Primary School

Axter Ltd

We were brought in by Middlesbrough Council to complete the roof refurbishment of Abingdon Primary School.Systems in useExcel®Starcoat® ROverviewWe had originally worked with Middlesbrough Council to complete Abingdon Primary School’s first phase of the roofing in 2015, and were asked to review the remaining flat roof areas to bring them in line with the previous phase.ChallengesWith this being a school, all works had to happen outside of school terms, so works began at the beginning of the summer holidays and had to be completed before the start of the September term. This on its own posed challenges to make sure that all roofing works were completed on time so as not to disrupt any of the children’s educations. Logistics were crucial, as was collaboration between Axter, NT Sweeting and Middlesbrough Council.There was also the issue of combustible areas around the perimeter of the building with some cladding details and some windows that could not be detailed in a traditional torch on application.SolutionsWorking closely with Middlesbrough Council from the outset, we surveyed the roof area and ensured the new waterproofing and previously completed phase were compatible. We also liaised closely with NT Sweeting to make sure all products were available and delivered to site on time to avoid unnecessary delays to the roofing works.Our Excel reinforced bitumen membrane system was specified for the main roof area; the membrane is manufactured with the unique Alpa polymeric binder, making it our most technologically advanced RBM system.Axter’s Starcoat R cold applied liquid bitumen PU resin was used to detail combustible items picked up in our report, including interface to windows and cladding abutments in line with Safe2Torch guidelines, which eliminated all fire risk.
Sponsored
Bath Riverside

Bath Riverside

Axter Ltd

Bath Western Riverside development is a multi-award-winning project for client Crest Nicholson Regeneration. The project has won multiple awards including the coveted NHBC ‘Pride in the Job’ award for H&S and the seal of excellence for quality.Systems in useExcel®ChallengesThe ‘curved’ bulk-heads, walls and interior finishes presented a special challenge to our on-site team, one that would be present over multiple floors and apartments.The system needed to be both robust and aesthetically pleasing, as the roofs are overlooked by residents and used as amenity spaces, and the colour had to be in keeping with the traditional Bath stone.In addition to this, the project featured many unique and complex terraces in terms of shape, threshold height, u-value requirements and access.SolutionsTo achieve both a level threshold and a good thermal performance, we designed a unique tapered insulation scheme for the terraces, utilising our Excel system, reinforced bitumen waterproofing membrane, in combination with our high performance and cost effective Hytherm VIP (Vacuum Packed Insulation) insulation scheme.To meet the aesthetics guidelines dictated by the local planning authority, the capsheet membrane was specified with a white granular finish, which provided the unique look the authorities were looking for.To ensure the terraces were installed correctly and in accordance with Axter requirements, we worked in close partnership with the development construction team. In conjunction with Avonside, a ‘traffic light’ system was introduced to ensure that each individual terrace had been checked by our Quality Assurance team, that it had been independently integrity tested and that it was installed in accordance with the architect’s details, upon which the guarantees were issued and the finishes thereafter installed.
Sponsored
BedZED

BedZED

Axter Ltd

The sustainable features of this ‘carbon-neutral’ development include excellent insulation, south facing terraces to maximise heat gain from the sun (passive solar gain) and structures built from natural, recycled and reclaimed materials, all sourced from within a 50 mile radius.Systems in useCityflor®Extensive Living RoofOverviewBeddington Zero Energy Development (BedZED) comprises a development of 82 homes in the London Borough of Sutton and is the UK’s largest mixed use sustainable community. It was designed to create a thriving community in which ordinary people could enjoy a high quality of life, while living within their fair share of the Earth’s resources.ChallengesAxter were tasked with providing a waterproofing and living roof solution for the garden terraces and higher level roof areas. As this was an environmentally-friendly housing development, careful consideration had to be taken to adhere to the sustainability requirements of the project. The thermal efficiency of the development was an essential design consideration with all roof areas needing to meet demanding thermal performance criteria. Lightweight extensive green roof systems were chosen for curved and sloping sections of the building due to their low maintenance characteristics, combined with high efficiency Solar PV renewable energy (BioSolar) systems on the roofs. Combining roof top planting with Solar PV improved the system performance and provided a positive visual impact.SolutionsCityflor multi-layer warm roof waterproofing system was designed and specified by Axter to meet the project’s demanding sustainability requirements. The use of a robust air and vapour control layer (AVCL) low permeability membrane, was installed to ensure the building was quickly made watertight during construction, whilst performing the critical technical function of controlling the movement of air, water vapour and heat leakage from within the building.The ideal capsheet choice for the development was our BBA accredited Force 4000 Trafic membrane, due to its anti-root technology and long term proven compatibility with living roofs. The installation of Force 4000 Trafic provided a robust waterproofing surface upon which the extensive living roof could be installed without risk of damage to the waterproofing by follow on trades.Extensive living roofs typically have thin (80mm) growing medium/substrate layers to keep the system depth and saturated load imposed on the building to a minimum. The Hydrolite extensive living roof system was specified because of its ultra lightweight growing medium as this weight reduction was ideal for the project’s unconventional structure. The Hydrolite living roof system was completed with a low maintenance planting design, utilising hardier, more drought tolerant plant species. The planting style was naturalistic with the aim of establishing self-sustaining plant ecology on the roof.AcknowledgmentsAxter worked closely with the project design and construction team to ensure that we were able to deliver a truly stunning and successful project.RAM Roofgarden LTD
Sponsored
Bexley Park Sports & Social Club

Bexley Park Sports & Social Club

Axter Ltd

Bexley Park Sports and Social Club is home to a wide range of sporting facilities and teams, including bowling, squash, football and rugby. They also have a large function room that is available for hire. Read on to learn how Axter was able to help them with a complete roof refurbishment.Project overviewThe original roof had been on the building for over 40 years. It was coming to the end of its serviceable life and was starting to show signs of aging, such as leaks around the rooflights.Axter were brought in to carry out the roof refurbishment of the main building.Overall, this project ran very smoothly and we were incredibly happy with the result. The writing on the barrel roof was a lovely added touch by our Axtershield Installer partner, Henley’s Roofing Ltd.This case study will focus on the main roof. However, as we will touch on towards the end, the client was so pleased with the work that they decided to go on to refurbish the other three roof areas.ChallengesThis was a complex project for several reasons. Several different parts of the main building had been added over time, so there was a change of level details throughout the roof.Part of the building had a barrel roof section, which added an extra level of complexity to the job.As well as this, there were a few existing features, such as a water tank on the roof surrounded by rotten chipboard, which also had to be taken into consideration when it came to planning installation methods.SolutionsGiven the age of the roof and the defects observed, it was recommended that a full overlay be carried out.As well as the specific roofing considerations, Bexley Park Sports and Social Club were looking to keep within a tight budget. For this reason, the single layer overlay solution worked perfectly to provide a cost-effective option. Our Reinforced Bitumen Membranes (RBM) combine strength with longevity to provide a durable waterproofing system with a 20-year guarantee.The rotten chipboard was removed and replaced with timber cladding. Flame free Starcoat® PMMA (polymethyl methacrylate) was used for the sections where it was necessary to eliminate fire risk. This cold-applied liquid system provided a great non-flammable solution.Systems in useExcel®Starcoat® PMMAAdditional works carried outThe client was very impressed with the quality of the work carried out on the main roof, and our ability to provide them with a cost-effective solution. The work came in under budget and they were so pleased with the job that they accelerated the project and decided to refurbish the other three club roofs – something that hadn’t been on the cards before. The initial work had provided them with the peace of mind that everything would go to plan and enhance the building, all with minimal disruption to the club. So we went on to refurbish the squash court, changing rooms and storage room roofs.Condition surveys were taken across all four of the roof areas. The additional roofing areas all needed re-decking as they were incredibly warn from ongoing water ingress.This meant we had to strip down to and remove the existing support structure, before installing a new ply deck, ready for the waterproofing works to go ahead. The changing room roof was pitched, adding an extra complexity to the job, as the shingle had to be replaced.
Sponsored
Castle Park View

Castle Park View

Axter Ltd

On the site of a former ambulance station, this project is situated in Castle Park, the largest urban green space in Bristol. It provided 375 new homes, through a mixture of Build-to-Rent and affordable dwellings.OverviewThe £90million Castle Park View is an exciting, award winning (Best Residential Development - Bristol Property Awards) and attractive new-build residential scheme, designed by Architect Chapman Taylor and built by Bouygues UK.This project included the regeneration of a brownfield site owned by Bristol City Council and Homes England in a prime location on the south-eastern corner of Castle Park. The development includes communal facilities, amenity space, and car parking, together with vehicular access, servicing arrangements, public realm works and landscaping. Now completed, this has set the benchmark for high rise development within the Bristol skyline, topping out at 26 storeys.Systems and productsThe client’s requirements called for a robust, extensive and holistic waterproofing system guarantee. Through Axter's vast system and product portfolio, the selection was made for a combination of Hyranger® and Cityflor® reinforced bituminous waterproofing systems, with allowance for cold applied liquid detailing where complex penetrations and compliance with NFRC Safe 2 Torch requirements were present. In such instances, Axter's Starcoat® PMMA and Starcoat® R cold applied bituminous PU liquids were used.In accordance with BS 6229:2018 section 4.4 Roof falls to achieve drainage, the concrete structure proved too complex for falls to be created with the traditional method. As such, a series of complex tapered insulation designs were completed to meet the requirements - both thermally, and to ensure a minimum of 1:80 finished falls were achieved.ComplexityGiven the regeneration of the brownfield site, it was critical to everyone involved that none of the wildlife and vegetation previously found at the site was lost. The implementation of Axter’s bespoke, bio-diverse brown roof with seeded mix was required to enhance the built environment and provide a habitat for the native species of wildlife and flora.To create the high-rise elements and visual representation of traditional castle turrets, albeit in modern form, the cladding panel detail required a bespoke castellation bracket fixed through the main roof structure of Block C. It was necessary for this to be accessed at various times during the build process. This required a complex sequence of works and the use of a cold applied liquid system.This project, like many across the UK, was hit by the outbreak of COVID-19. Extensive delays to the build programme were a challenge, plus complexities within the market through shortage of labour, transport and raw materials. Both Axter and NRA Roofing & Flooring Services Ltd worked tirelessly with the key stakeholders, such as Bouygues, to ensure timely supply and delivery of all materials was made through additional storage capacity, off site storage, negotiation and rigorous project planning. This involved collaborative open dialogue, regular workshops and project reviews.Due to the site’s location, the infrastructure and layout of roads meant that all deliveries were required to be on a strict timed system including all allowances for offloading and lifting within a tight time period. This required meticulous planning and allowances with very little margin for error or delay. In a time where COVID guidelines restricted contact to a minimum of two metres, it was incredible to see all parties work so well together to ensure these windows of time were met.Project managementAlthough all roofs were finished with a traditional three-layer bituminous membrane finish - including a tapered cut to falls insulation scheme - the project comprised a variety of roofing finishes including brown bio-diverse roofs, decorative paving and solar panel installations.Daily logistics meetings were held with all parties to co-ordinate and plan the most efficient way of undertaking each phase of the works, thus maintaining safety and efficiency at all times throughout the project.The roofing scheme was successfully delivered and handed over in April 2022 which was within the very tight programme deadlines, despite the delays and complications provided by the pandemic which inevitably led to a significant number of complications.NRA Roofing & Flooring Services Ltd were able to successfully deliver the installation of the complex amenity area to one of the roofs which included a significant area of decorative large profile ceramic tiling on pedestals, as well as an outdoor cooking area, planters and green roof areas to the tops of sheltered seating spaces.At handover, Bouygues expressed their sincere gratitude to NRA Roofing & Flooring Services Ltd in being able to deliver this highly complex, multi-faceted city centre project successfully in terms of safety, on time and within the agreed contract budget.Systems in UseHyranger®Cityflor®Starcoat® PMMAStarcoat® RknowledgmentsWe have been working closely with Axter for a number of years across our regions, during which time they have become a vital part of the supply chain, from early stage design and costing to the successful delivery of robust, guaranteed waterproofing systems.With a vast product portfolio, BYUK are confident that the build requirements and production timescales will always be met. With programme being such a critical element of the build, this reassurance is welcomed by the wider team.– Joseph Southwick, Package Manager - Envelope Bouygues UK
Sponsored
Centenary Quay

Centenary Quay

Axter Ltd

This project was part of the vibrant regeneration of Southampton’s waterfront, including 102 apartments with high rise penthouse flats, retail and commercial space. Phase three of the project incorporated a bio-diverse living roof as well as amenity space built above a Morrisons supermarket.ChallengesWith fully accessible amenity gardens including a flowing water feature, it was vital a robust specification was delivered. Due to this space being built above a Morrisons supermarket, careful design consideration was essential to ensure that Axter’s driving philosophy of the right system in the right place was successfully employed.SolutionsFor the main roof area, a robust system was required. The Wilotekt-Plus was specified for system on the podium, main roof and terraces (5000m2). This system is the original and industry renowned second generation hot melt structural waterproofing system. Its pure polymer modified bitumen compound formulation, combined with reinforcement mesh and high strength protection membrane, resulted in a tough, seamless, flexible, self-healing monolithic waterproofing system, with incredibly fast installation speeds, that will last the lifetime of the building.Ecoflex PVC single ply waterproofing (450m2) installed on the canopies, idea due to the system being incredibly lightweight, typically 2-3kg per m2. Ecoflex systems are strong and flexible, are fully reinforced and available for mechanically fixed and adhered applications.Working alongside horticulture specialists and substrate and seed providers, we ensured all elements of the roof complied with the Biodiversity Design Report for the development. This included specially selected grass and flower species, chosen for their ability to withstand windy coastal conditions. When established, these plants will provide shelter and forage to a range of invertebrates and birds.Systems in useWilotekt®-PlusEcoflex®Biodiverse Living Roof
Sponsored
Desborough Library

Desborough Library

Axter Ltd

Axter Ltd and Empire Roofing Systems Ltd were engaged by the library directly to upgrade the existing roof covering which was underperforming thermally and in terms of drainage falls.Systems in useHyranger®Neo-Bitumen® Flame FreeStarcoat® PMMAOverviewDesborough Library and Community Hub took over responsibility for the running of the library service in Desborough in 2020. With that came the maintenance of the library building itself. Over time, certain parts of the building had deteriorated. There were leaks and sections of standing water across the 100 square metres plus of flat roofing that forms part of the roof structure.The client applied to The National Lottery Community Fund for a grant that would be used to refurbish the roof area. The Library and Community Hub were fortunate enough to obtain the necessary funding for the work to go ahead.An overlay of the existing system was proposed to utilise the current build up, including a cut to falls insulation scheme to comply with Building Regulations Parts L & H, and BS 6229:2018. Safe2Torch principles were followed throughout with some creative detailing agreed between the contractor and manufacturer due to combustible elements and areas of asbestos.An excellent finish was achieved within budget and in a timescale of 3 weeks.ChallengesAxter were brought in following initial core sampling that was completed by Empire Roofing Systems. The roof area was assessed, and a robust solution was proposed which would alleviate the standing water seen across the roof area, while also improving the thermal performance of the building up to a 0.18 U-Value to comply with Building Regulations: Part L.The existing system was in fair condition but had reached the end of its guaranteed life with no leaks reported and core samples returning dry. There was a noted lack of maintenance across the roof area and significant challenges apparent in terms of detailing due to fire risks and asbestos present.SolutionsBased on the condition of the existing system we were confident that an overlay would be the most cost-effective option. Our Hyranger® multi-layer RBM system was installed using gas driven torches to fully bond the AVCL and capping sheet. The underlayer was installed over a tissue faced PIR and therefore needed to be self-adhesive to reduce the risk of fire, complying with Safe2Torch guidelines. Our hot air applied Force® Neo Bitumen system was installed in the areas of fire risk, and our cold applied Starcoat® PMMA liquid system was installed in areas where a hot air application would be problematic.A cut to falls scheme was designed based on our onsite survey, allowing water to flow freely to the outlets. This alleviated the risk of water buildup and thermal degradation caused by ponding water.Axter’s quality assurance team regularly attended site and were in constant communication with Empire Roofing’s operatives. This was to ensure that the system was being installed correctly and to the expected standards, in order to achieve the Silvershield guarantee required by the client. To achieve the Silvershield guarantee level, all materials and workmanship had to be installed as per the Axter specification. The installation of the roof area was completed to exceptional standards, leaving the client very impressed with the workmanship.System and ProductsAxter’s Hyranger® system was used across the main roof area. The system is fully BBA and Broof T4 compliant, and comes with a single point 20 year Axter Silvershield guarantee that covers materials and workmanship. This was signed off by our Quality Assurance Team who audited throughout installation.Safe2Torch principals were adhered to throughout. Our Neo-Bitumen® Flame Free system was predominantly used on any areas of fire risk, as well as our Starcoat® PMMA for the tricky details where a comprehensive weld may not have been possible.Acknowledgments"We knew of Empire Roofing Systems from another good job they had completed for us on a separate part of the building, and asked them to quote for repair of the troublesome flat roofing.Empire and Axter came up with a plan to make the roof drain properly and we went ahead with their quote.The work went ahead on schedule and to plan without any disruption to the running of the Library and Community Hub and took around two weeks to complete.The guys worked hard and were always helpful and polite when we asked any questions about the work in progress. We had an issue with a blocked internal drainpipe which was quickly and effectively dealt with by Jim and his team from Empire.We are delighted with the end results and have the assurance that the work has been inspected by technicians from Axter themselves and comes with their written guarantee." Gil, Desborough Library
Sponsored
Durham Lane Primary School

Durham Lane Primary School

Axter Ltd

This project for Durham Lane Primary School saw the refurbishment of their existing roof. The previous bitumen waterproofing was showing signs of wear. Isolated areas of leaks had started to form, which was presenting classroom disruption.ChallengesFor funding purposes, the roof area was inspected and separated into two phases. Phase 1 of the roofing works presented a number of potential fire risks with combustible substrates and penetrations. The existing make-up performed poorly when tested against current building regulations.SolutionsFollowing minor remedial works, the existing waterproofing system was inspected and deemed suitable for use as the air and vapour control layer. Thermal and acoustic upgrades were introduced through the installation of Hytherm MW mineral wool insulation, ensuring building regulation compliance and an acoustically sound teaching environment in compliance with BB93.To complete the installation, Hyranger reinforced bitumen waterproofing system was installed, achieving a 20 year insured guaranteecovering waterproofing system materials supplied by Axter. In accordance with the NFRC’s Safe2Torch guidance, cold applied liquid waterproofing was required for detailing to fire risk areas; in this instance, Starcoat R was the system of choice due to uniform aesthetical finish and cost efficiency.Systems in useHyranger®Starcoat® R
Sponsored
Dylon Works

Dylon Works

Axter Ltd

A high profile 0.7 hectare residential development, completed in 2017. This project featured the Aquamodul warm blue roof, one of the largest schemes of its kind ever achieved within the capital.ChallengesThe project presented significant challenges, such as demanding thermal performance criteria combined with a challenging planning requirement to achieve maximum outflow rain water run off rates of 10l/s across the entire 7500m2 site.SolutionsThe design and implementation of a site wide blue roof ensures the development’s contribution to mitigating flood risk in London and supports the protection of England’s waterways. Modelled over a 300 year period, the blue roof design is future proofed in terms of its provision for likely climate change and increases in predicted peak rainfall events.Second generation hot melt structural waterproofing system, Wilotekt-Plus, was installed as the Air and Vapour Control Layer (AVCL), which provided an extremely robust waterproof structure during the external envelope and superstructure construction phase. Hytherm ADH thermal insulation and BBA accredited Force Dalle bitumen membranes with anti-root technology where later installed to complete the waterproofing and insulation system.Prior to hand over and installation of the Aquamodul blue roof attenuation cell, the waterproofing system was integrity tested using a differential pressure testing method by independent specialists to ensure the roof was watertight. Once passed as secure, the Aquamodul blue roof cassette and biodiverse (brown) living roof finishes where installed with the further addition of a PV panel array generating the majority of the building’s electrical energy requirements.Systems in useForce Dalle®Wilotekt®-PlusAquamodul®
Sponsored
Early Learning Unit (ELU)

Early Learning Unit (ELU)

Axter Ltd

The Early Learning Unit (ELU) in Hamilton was relocating to the former Hamilton Grammar School site, which had been demolished the previous year. Axter were brought on board to determine the best type of roof that would provide the greatest benefit to the school and its pupils.ChallengesThis project was originally specified to be a single ply system but, with the school catering for children with special requirements, it was decided that a living roof system would be beneficial to both the staff and pupils, and that single ply would not be suitable.This is when Axter and Procladd became involved in this project and worked together to design a robust waterproofing system that could work with a living roof, and still provide value for money for the Council, whilst delivering the project on time and on budget.SolutionsFollowing discussions, Axter’s Cityflor Reinforced Bitumen Membrane system was specified over a plywood substrate, with an extensive green roof. This project presented some unique challenges, specifically in the need for the use of Flame Free Technology to combustible upstands. Axter and Procladd were both committed to NFRC Safe2Torch standards, with Axter’s Flame Free Neo-Bitumen Technology specified on upstands to remove any risk of fire. The Force 4000 Flame Free system to these areas consisted of a self-adhesive binder, combined with hot air welding technology to seal and bond all laps, to ensure a robust detail without any risk of a naked flame near combustible materials.When asked to comment on using the Neo-Bitumen Flame Free technology, Procladd Operatives Billy and John commented: “The membrane was very easy to work with and a pleasure to install. The self-adhesive membrane adhered incredibly well to the upstand without the need to heat the underside, like a standard torch applied system, which made the installation a quick process. Once completed we heated the side and head laps using a hot air gun, normally associated with Single Ply membrane, to ensure a full bond complete with a 2mm bitumen bead. The system is one of the most straightforward and workable systems that we have used.”Procladd Managing Director Keith Burrell said, “We have worked with Axter on a number of projects and knew, through their commitment to achieving robust waterproofing systems, and their experience within the education sector, that it meant we could work together to complete this project in harmony to give the best service possible to South Lanarkshire Council.The introduction of their Flame Free Neo-Bitumen system to the areas of combustible upstand meant that works could progress quickly on site, whilst maintaining safety and reducing any risk of naked flame near to timber or combustible materials.From start to finish Axter were informative and helpful with initial NBS specifications, detailed drawings and thermal calculations, right through to on site technical guidance and Quality Assessment of the ongoing works and through to completion and Guarantee.”AcknowledgmentsWe have worked with Axter on a number of projects and knew, through their commitment to achieving robust waterproofing systems, and their experience within the education sector, that it meant we could work together to complete this project in harmony to give the best service possible to South Lanarkshire Council.The introduction of their Flame Free Neo-Bitumen system to the areas of combustible upstand meant that works could progress quickly on site, whilst maintaining safety and reducing any risk of naked flame near to timber or combustible materials.From start to finish Axter were informative and helpful with initial NBS specifications, detailed drawings and thermal calculations, right through to on site technical guidance and Quality Assessment of the ongoing works and through to completion and Guarantee.Keith Burrell - Managing Director, Procladd
Sponsored
Escapade Silverstone

Escapade Silverstone

Axter Ltd

Escapade Silverstone is a unique new commercial development sat right on the edge of the iconic Silverstone circuit.This prestigious project is comprised of 60 residences, a club house and car storage.The development is due to be completed in 2024, ready for next year’s Grand Prix.It will operate as short-stay accommodation for both the major calendar events and for the rest of the year when people are out on the track testing cars, etc. Escapade guests will be able to enjoy all that Silverstone has to offer.Axter were involved right from the outset. There were lots of complexities with the project, due to the nature of the design and the architect’s intentions, so we were able to recommend different solutions for different sections of the roof.Our video case study shows the progress so far. It's such an exciting project to be a part of and it was great to see the finishing touches being made to the waterproofing works by Embassy Site Services.Wilotekt®-Plus has been used on the new clubhouse and our Ecoflex® system has been specifically chosen for the residencies.It’s been a pleasure to work with Escapade, HG Construction and Embassy Site Services on this project and we can’t wait to revisit the site next year to check out the finished development. Stay tuned for our next video.Systems in useWilotekt®-PlusEcoflex®
Sponsored
Fulham Wharf

Fulham Wharf

Axter Ltd

This project was a re-development of an existing supermarket together with the adjoining Fulham Wharf site. It comprised the new 100,000 sq. ft store and 463 residential units with their own balcony and terrace, many with views over podium gardens and the River Thames.Systems in useWilotekt®-PlusEcoflex®Starcoat® PMMAStarcoat® QCStarcoat® RChallengesThis was a challenging site logistically with limited delivery and site access points, and the project had to be completed with consideration being given to residents and with the existing supermarket remaining fully operational. The waterproofing system had to be monolithic, fully adhered to prevent water tracking during and post construction, robust, durable and capable of withstanding construction-related traffic without defect.SolutionsCareful design consideration was provided to ensure Axter’s driving philosophy of the right system in the right place was employed successfully. The design, supply and installation of Wilotekt-Plus, unique second generation hot melt structural waterproofing system, provided 30% quicker on site installation speeds than traditional first generation hot melt systems. This ensured the waterproofing was completed swiftly, which enabled landscaping finishes to be installed within deadline.Wilotekt-Plus also fulfilled the requirement for a system that was adaptable through its approved application beneath a variety of roof finishes including ballast, decorative paving and living roofs, so as to facilitate the achievement of interesting visual aesthetics, enhancing built environment and life experience of its residents.
Sponsored
George Eliot Hospital

George Eliot Hospital

Axter Ltd

The NHS Estates Team required a new office space and workshop area and proposed the refurbishment of an existing building.Systems in useHyranger®Starcoat® PMMAOverviewAxter Ltd were instructed by William Gough & Sons Ltd to produce a design for six roof areas, following a site survey report. The project included a mixture of new build and refurbishment areas, comprising of various systems and design requirements. This included a cut to falls insulation design to comply with Part H and BS 6229:2018. Roof A, the focus of this case study, had a series of convex or ‘barrel roofs’, requiring bespoke detailing and careful design to achieve robust detailing and the required U-value.The project value was circa £1 million. This included all building works and a strict budget for the roofing package, which was achieved. The programme for the works was 16 weeks and completed in Autumn of 2022, to the required deadline.The successful project was also nominated for a National Federation of Roofing Contractors (NFRC) award 2023.ChallengesAxter were appointed at RIBA Stage 2 to undertake site surveys and work alongside the Principal Designer as Designer under the Construction Design and Management Regulations 2015.The existing asphalt had shown signs of cracking and blistering, and the outlets were damaged from vegetation growth from a lack of maintenance. New outlets were installed with leaf guards, allowing free flowing water whilst preventing blockages.The proposed office section of the works required thermally upgrading to comply with Building Regulations: Part L. The U-Value requirement was 0.18W/m2K which could be achieved with a 120mm PIR flat board. Due to the curved profile of the roof, installing the insulation below deck level was considered. However, due to an inadequate ceiling height this was disregarded.Furthermore, this would have resulted in the development of interstitial condensation. Further design solutions had to be considered. To bend a 120mm board would have required multiple cuts to the insulation so the decision was made to split this into two thinner boards to achieve the radius more easily.When split into two layers the requirement changed to 2 x70mm boards (140mm total) as worked out using U-Value calculations by the in-house design team at Axter. A timber hard edge was introduced to abut the insulation at the building perimeter to separate the façade and the main field area.Systems and productsAxter’s Hyranger multi-layer RBM system was used across all six roof areas. The system is fully BBA and BRoofT4 compliant, and achieves a guarantee period of 20 years. For this project, Axter’s Goldshield Guarantee was chosen, which covers materials, workmanship and design liability. This was overseen on site by Axter’s Quality Assurance team, who audited the project inclusive of the installation, safety and general management of the roofing works.Axter Starcoat PMMA was used as a cost effective solution to coat the copper fascia and provide a fresh and seamless look to the exterior of the building.SolutionsThe Axter Hyranger multi-layer RBM system was installed using traditional gas driven torches to fully bond the (AVCL) Air and Vapour Control Layer and cap sheet layers. The underlayer was installed over a tissue faced PIR and therefore needed to be self-adhesive in order to reduce the risk of fire, complying with NFRC Safe2Torch guidelines. A cold applied Starcoat PMMA liquid was installed to the façade to achieve a seamless and cost-effective upgrade.The Axter Quality Assurance Team regularly attended site and were in constant communication with the appointed Axtershield Installer, Empire Roofing operatives, to ensure that the system was being installed correctly and to the expected standards in order to achieve the Goldshield guarantee required by the client. To achieve the guarantee level, all materials and workmanship had to be installed as per the Axter specification.The site agent from the main contractor was also regularly on site to oversee the project and ensure that deadlines and timescales were being achieved to keep the build on target for completion. The installation of the multiple roof areas was achieved to exceptional standards leaving the client very impressed with the workmanship.AcknowledgmentsWilliam Gough & Sons Ltd were very impressed with Axter Ltd on our first scheme with them at George Eliot Hospital in Nuneaton. The requirements of the scheme, which included a complex barrelled roof were investigated on site early in the design phase of the project and Axter’s recommendations were swiftly proposed and agreed with the client’s Architect. Once the design requirements had been established one of Axter’s approved installers were employed by us to very successfully deliver the scheme. The 20 year Goldshield guarantee provided for the Reinforced Bituminous Membrane system offered peace and mind to our client. Chris Hinton, Senior QS, William Gough & Sons
Sponsored
Henderson Building

Henderson Building

Axter Ltd

This building was once home to the Henderson Garage door production facility, with the client in the process of renovating the entire premises to be split into several new warehousing and office units. To be able to secure new tenants, however, there was an urgency to stop a mass amount of water ingress into the building, due to the roof's years of neglect.Systems in useHyranger®Starcoat® RChallengesThe state of the existing waterproofing was poor, meaning it needed to be stripped back to the metal deck below. Given the years of water ingress it was clear some areas of the substrate were deteriorating and would need replacing.There was also an issue with the adjacent metal cladding to the perimeter of the roof space, one of which was coated in an asbestos paint and the potential for asbestos rope within the old rooflights. All of this needed addressing prior to the roofing works commencing.SolutionsAxter were called to initially survey the roof area, highlighting the main areas of concern and interface issues. Following a roof condition survey report, proposals were put forward as to how best to detail waterproof these areas and achieve the brief set out by the client.To the metal cladding, Starcoat R cold applied liquid bitumen PU resin was used to create a waterproofed upstand without the need for the complete removal of the cladding. Upon discussions with the building owner, it was also discovered that the existing rooflights were no longer needed, so these were boarded over and waterproofed in line with the rest of the main field area.The Hyranger system, comprising polyester reinforced SBS polymer modified bitumen membranes, was ideal for the job due to its guarantee strength, stability, performance and cost efficiency.The completed roof gained a 20 year guarantee and extended the life of the building.
Sponsored
Jolley Ford Court

Jolley Ford Court

Axter Ltd

Axter were called to investigate the condition of balcony walkways on this residential project, which appeared to be deteriorating.ChallengesOur technical team completed a roof condition survey and found that the existing system had significant cracking, notably at the joints of the substrate board, which had caused water to penetrate the system. This cracking indicated a lack of suitable flexibility within the resin compound and there were no movement joints to help compensate for this.Over time, these cracks in the field area would have worsened due to expansion and contraction caused by the changing weather. The ridges would have become more pronounced, leading to greater water ingress, trip hazards and potential injury. There was no drip trim installed to the external edge, so water was able to track under the deck and present as a leak, damaging the soffit below. With residents living in the block and requiring access to the walkways, it was important that the refurbishment works would not impair their movements too greatly, or impact them with noise, hot works and other associated hazards.SolutionsIt was not practical to remove and replace the existing system, so an overlay was essential. The Starcoat PMMA system provided the ideal solution as it had the flexibility to accommodate the walkway movement whilst minimising the impact on the residents. The system assembly included a hard-wearing, self-levelling mortar and anti-slip aggregate designed to withstand heavy traffic and resist any potential damage from pedestrian access. A bespoke coloured sealer was also applied to the waterproofing system to match the existing metal works and colour scheme on the project.As the system is rain-proof in approximately 20 minutes and trafficable in around one hour, this meant that the access route could always be maintained and all internal detailing around residents’ front doors could be easily co-ordinated.As Starcoat PMMA is a flame free system, compliance with all NFRC Safe2Torch recommendations was achieved. This was essential considering the presence of combustible materials such as doors and frames.No requirement for gas or heating equipment on site also meant that the level of noise was kept at a minimum, with only a paddle mixer and hand tools being used to complete the installation. To further limit the potential impact of the works, a low odour system formulation was used.A metal trim was introduced at the external perimeter, allowing water to run off and prevent any capillary action back under the substrate boards and into the system.Axter Alliance Installer, Blue2 Contractors Ltd, worked efficiently and to a very high standard to complete the project in under a week, delivering an aesthetically pleasing, effective and robust waterproofing solution.Systems in useStarcoat® PMMA
Sponsored
Kensington House

Kensington House

Axter Ltd

Our technical team were invited to complete a roof survey and condition report of this residential project, where the existing roof area which was suffering from repeated leaks, failed repair attempts and significant standing water.ChallengesUpon inspection it was clear the roof covering had been recently renewed, but the workmanship, attention to details and drainage falls were sub-standard and no doubt contributory to the ongoing leaks and consequential ceiling damage to the areas below.Although the client preferred a robust torch-applied reinforced bitumen waterproofing system, our Safe2Torch assessment picked up some redundant roof plant, combustible cladding interfaces and complex penetrations which necessitated a localised flame free solution.Our team also carried out a level-survey to ascertain the existing falls, and what, if anything, could be done to alleviate the standing water without excessive cost.SolutionsOur comprehensive roof survey report included a dimensioned roof plan, identification of Safe2Torch areas/details, bespoke waterproofing designs for complex penetrations, and a thorough assessment of the existing roof make-up (via core samples) and drainage.Given the apparent age and good condition of half the roof area, it was left in-situ and overlaid with Hyranger single layer RBM system. Minor improvements to the drainage layout, via the introduction of a tapered insulation scheme central to the roof where the outlets where positioned, helped to significantly improve falls. Elsewhere, the rest of the existing roof covering and thermal insulation were stripped back to expose the original asphalt.The asphalt received a new air and vapour control layer before the same Hyranger system, including a mix of both flat board and tapered Hytherm ADH insulation, was installed to improve the falls and correct the thermal performance balance.A Safe2Torch abutment detail to existing cladding was identified early on in the Axter roof survey report as a fire safety hazard, so in accordance with our specification and recommendations, our accredited Axtershield Installer - N R A Roofing & Flooring Services Ltd - expertly installed a Hyranger Neo-Bitumen Flame Free membrane solution around a 900mm wide margin.The Axtershield Installer worked efficiently and to a very high standard to complete the project on budget whilst delivering an aesthetically pleasing and robust waterproofing solution.Systems in useHyranger®Neo-Bitumen® Flame Free
Sponsored
Kensington Roof Gardens

Kensington Roof Gardens

Axter Ltd

The multi-million pound refurbishment project saw the iconic building and its landscaped gardens restored to their former glory. Axter’s cold applied liquid waterproofing systems delivered a high quality solution to this challenging refurbishment.Systems in useStarcoat® QCStarcoat® PMMAKensington Roof Gardens is one of London’s best known venues, once famous for its flamingos and celebrity guests. The Grade II listed gardens were designed by landscape architect Ralph Hancock and date back to the 1930s. The venue features one of Central London’s most famous intensive living roofs and also includes an indoor restaurant, entertainment space and elevated terracing.ChallengesThe refurbishment of Kensington Roof Gardens was technically demanding. This was due to the complexity of the waterproofing details and space restricted installation locations as well as the specific waterproofing requirements.The refurbishment of the pond and waterways required a liquid waterproofing system that is proven to be safe for aquatic life, is UV stable and meets the aesthetic requirements. In addition, the waterproofing for the elevated terraces and walkways needed to be robust, rapid curing and appropriate for high traffic areas with a high quality, anti-slip finish.SolutionsAxter’s Technical Sales Team was able to provide BBA approved liquid waterproofing specifications for both areas. Axter ensured the highest quality waterproofing installation in all areas.Starcoat QC flame free single component PU resin waterproofing was used for the pond and waterways. The system cures fast in just 4-8 hours depending on the conditions and creates a tough, seamless, elastomeric membrane. This makes it ideal for complex refurbishment projects, such as Kensington Roof Gardens, where effective bridging of cracks and resistance to structural and thermal movement is essential. The robust, solvent free membrane also simplified the waterproofing of the site’s complex details and is resistant to chemicals and root penetration.The Starcoat PMMA (polymethyl methacrylate) two component waterproofing, used on the walkways and terraces, is zero fall accredited, hard wearing and can withstand significant loading and mechanical stresses. Available in a choice of colours, traffic and anti-slip finishes, it also provides an excellent solution for complex detailing and challenging application areas.AcknowledgmentsThe refurbishment of the iconic Kensington Roof Gardens demonstrates the versatility of our Starcoat PU and PMMA liquid waterproofing systems. Working closely with our partners, we were able to provide a high-quality technical solution that benefits from a 25-year system guarantee.Phil Wilcox Moore, Managing Director at Axter
Sponsored
King Solomon School

King Solomon School

Axter Ltd

OverviewThis project saw the refurbishment of King Solomon International Business School, which was changing hands from office use to education. The building now features specialist science rooms, resistant materials workshop, drama studio, outdoor sports hall, music rehearsal rooms, food technology, ICT rooms and language rooms.ChallengesDue to the change of building use, a full survey of the roof covering was required. Excessive moisture was found within the existing asphalt covering, water ingress was present and the internal top floor of the building was not suitable to be used as a teaching space. The roof area presented many challenges with complex detailing to existing balustrade posts, live mobile telephone masts and large quantities of plant / M&E installed.SolutionsAs a starting point, the roof was completely stripped due to the high level of water ingress. The existing asphalt covering was removed ready for installation of a new Excel RBM system, with Hytherm ADH PIR thermal insulation. Much of the existing M&E was found to be redundant and could safely be removed from the roof area.The complex detailing to the balustrades and fire risk areas was simplified using Starcoat PMMA cold applied liquid waterproofing, allowing for a long term, robust and financially viable solution. High level roof areas were also detailed with ease using Starcoat PMMA. Successful installation provided a peace of mind roof covering for the next 25 years, supported by Axter’s Platinum Guarantee.Systems in useExcel®Starcoat® PMMA
Sponsored
Knighton Fields

Knighton Fields

Axter Ltd

After securing funding via the CIF application, Knighton Fields Primary Academy was able to address some of the long-term issues they had in relation their roof, which was beginning to show signs of wear.ChallengesThe existing waterproofing had been suffering with significant amounts of standing water, water ingress, structural deck failure (localised), poor thermal insulation, and several tired old and dilapidated lantern roof lights. All roof areas needed to be inspected and level surveyed and, in one localized area, the existing waterproofing and deck had to be entirely stripped and removed owing to significant deflection and fear of collapse. The works needed to progress swiftly so as to provide minimal disruption to the school environment.SolutionsAfter inspection, proposals were put forward for a tapered insulation overlay where deemed necessary, to help improve falls to existing outlets and rid the problem of standing water. In most instances, the existing roof covering was simply overlaid and formed part of the new Air and Vapour Control Layer (AVCL) before a new Hytherm ADH flat/tapered insulation board and two-layer fully adhered Excel RBM system was installed over this. On the area where the existing waterproofing had been stripped, the deck was replaced (to falls), a new AVCL installed and the same Excel warm roof system was carried through to complete these areas.Works progressed throughout the summer holidays to avoid any disruption to the school or pupils. NFRC Safe2Torch principles were observed, prescribed and employed as part of the scope of works. An Insurance backed Guarantee covering design, materials and workmanship was issued upon practical completion of the works and following successful sign off from the Axter in-house QA team (who monitored the procession of works from start to finish) to the client, indemnifying their risk and protecting the building and its occupants for a period of 25 years.Systems in useExcel®
Sponsored
Lily’s Walk

Lily’s Walk

Axter Ltd

This project was one of the largest schemes of its kind ever achieved outside of the capital, featuring the Aquamodul warm blue roof with our Force Dalle BBA approved system.Systems in useWilotekt®-PlusForce Dalle®Aquamodul®Extensive Living RoofChallengesThe roof attenuation rate required was 7litres/sec across the 6500m2, which is extremely low for such a large area, and the u-value of 0.10W/m2K was relatively demanding in terms of thermal performance. It was a project specific requirement that the roof was designed with falls within the slab in order to avoid any ponding water.SolutionsThe design and implementation of a site wide blue roof ensured the development’s contribution to mitigating flood risk in the UK, supporting the protection of England’s waterways. Modelled over a 300 year period, the blue roof design is future proofed in terms of its provision for likely climate change and increases in predicted peak rainfall events.Wilotekt-Plus, second generation hot melt structural waterproofing system, was installed as the Air and Vapour Control Layer (AVCL), which provided an extremely robust waterproof structure during the external envelope and superstructure construction phase. Hytherm ADH thermal insulation and Force Dalle bitumen membrane with anti-root technology were later installed to complete the waterproofing and insulation system.Upon final QA inspection and integrity testing of the roof waterproofing works, the Aquamodul blue roof system, bespoke Hydrosoil Wildflower living roof and standard ballast finishes were installed in conjunction with a Solar PV array, which generated the majority of the building’s electrical energy requirements.
Sponsored
Marrtree Business Park

Marrtree Business Park

Axter Ltd

Marrtree Business Park is a large warehouse estate, mostly made up of single storey industrial/warehouse units. A refurbishment of their roof was needed as part of a wider development, including full renovation of the office suite, new LED warehouse lighting and electrical installation.Systems in useForce®Starcoat® RChallengesOne significant challenge for this project was that the roof did not comply with current Part L building regulations and needed thermally upgrading as part of the building refurbishment works. There were also combustibility issues with the metal cladding to the perimeter of the flat roof area. Not only this, severe ponding water and delamination of the existing membrane meant poor drainage falls across the roof area.Access was also a challenge for this survey, with a scaffold having to be erected before the final roof condition report could be conducted, so time and turnaround was key to lessening additional costs for the building owner. Axter were able to conduct the survey and get recommendations and specifications to the main contractor and client within a 48 hour window, allowing the scaffold to remain in situ in preparation for works to commence as soon as possible.SolutionsAs the existing waterproofing was beyond repair, we recommended that it be completely stripped back to the metal substrate. In its place, the Force reinforced bitumen system was installed, which was idea due to its durability, flexibility and exceptional ageing characteristics.The system incorporated Hytherm ADH Tapered Insulation following on from a level survey to improve falls and upgrade the thermal performance of the building in line with current regulations.Axter’s Starcoat R cold liquid bitumen PU resin was employed to mitigate any potential fire risk to details, in line with the NFRC’s Safe2Torch guidance. A charcoal granule finish was added to this in order to maintain continuity of the RBM membrane aesthetic.
Sponsored
Newcastle Under Lyme College

Newcastle Under Lyme College

Axter Ltd

Upon the opening of a new Renewable Energy Training Course, Newcastle Under Lyme College decided to use the existing roof space of a recently constructed building to house a photovoltaic system, as both an investment and teaching opportunity.ChallengesThe new photovoltaic system was to be installed on the roof of the recently built Skills and Technology Centre. The existing structure, however, was neither designed or constructed to withstand the additional weight load of a ballasted crystalline PV array, and a mechanically fastened solution proved problematic.SolutionsLightweight (less than 7kg/m2), low profile (5mm build-up) and hard wearing (Teflon coated), the amorphous thin film Solar PV modules specified were the ideal product for this type of application. An outline PV array design and payback calculation were provided by Axter, and once instructed, the works were installed in a matter of days, with all of the modules and tooling being passed up through the Roof Access hatch. Axter’s lightweight, Velcro attached, building-integrated photovoltaic (BIPV) Solar PV modules offered a cost effective, safe and practical option, without penetrating the existing roof covering.
Sponsored
Park Central

Park Central

Axter Ltd

Park Central, Zone B11, Birmingham has been an ongoing 15-year project which Crest Nicholson Regeneration, delivered in partnership with Birmingham City Council and Optima Community Association.Systems in useWilotekt®-PlusEcoflex®Starcoat® PMMAOverviewThe development has completely transformed the former Lee Bank Estate into a desirable place for city centre living. Included in the scheme is an eight-acre park at the centre, which has proved very popular with the local community.ChallengesThe primary challenge was to achieve a robust waterproofing solution across all areas of the project, ensuring that all key targets of the construction programme, installation, cost efficiencies and client requirements are met.This coupled with ensuring all aspects of the waterproofing package were designed and installed in accordance with the current government legislation, NHBC design guide and industry design guides including BS 6229:2018, requiring all areas to be installed to a design fall no less than 1:80. Due to the roof slab being concrete, the frame required a fall within the structure to remove the requirement for a secondary screed which was simply accommodated across all areas. However, Block E proved a little more difficult due to the curvature of the building.SolutionsThrough review of Axter’s extensive system portfolio and by following our waterproofing ethos of ‘right system, right application’, a mix of three key waterproofing solutions was incorporated within the architectural design specification.Wilotekt-Plus was specified for the central podium as a robust waterproofing system, allowing for regular foot traffic and storage during the construction stage as this was a key area for use with deliveries and access to three of the six blocks. The system was also specified for the main roofs where a fall could be achieved within the concrete slab.Block E proved a little more challenging to create the fall, but Ecoflex ADH PVCp single ply with tapered insulation was more than up to the job. It was installed allowing for a clean, visually attractive aesthetic and the required design falls to achieve drainage.To close out the design and turnkey solution, we also incorporated waterproofing to the exposed car park decks between Blocks D and E and Blocks E and A with R12 rated, BBA certified Starcoat PMMA. Bay marking was easily applied using Starcoat PMMA white roller-applied surfacing.Through close collaboration and partnership with Axtershield Installer NRA Roofing & Flooring, all works were protected under Axter’s Platinum Guarantee, our most comprehensive insurance backed guarantee covering materials, design, workmanship and insolvency. The excellent workmanship, attention to detail and multi-discipline co-ordination of works displayed by our Axtershield Installer helped to deliver this complex project.
Sponsored
Plough Lane

Plough Lane

Axter Ltd

A high profile residential development located on the derelict site of the once mighty Wimbledon FC, completed in 2008.OverviewAxter designed and supplied a complete structural waterproofing, insulation, drainage and landscaping solution to all elevated podia. The areas were intensively landscaped combining hard and soft finishes, creating a mixture of meandering pedestrian walkways and landscaped recreational gardens with a combined area of 6000m2.ChallengesThe primary challenge was to achieve a robust structural waterproofing system that could provide construction programme design, installation and cost efficiencies.A complex site drainage strategy, combined with multiple hard and soft landscaped finishes of varying depths, resulted in the need for additional drainage and water retention measures to be designed and implemented throughout the site.A high cost and varied landscaping design, with a relatively short seasonal installation time frame, demanded a waterproofing system designer and manufacturing partner that could meet these challenges.SolutionsThe design supply and installation of Wilotekt-Plus, unique second generation hot melt structural waterproofing system, provided 30% quicker on site installation speeds than traditional first generation hot melt systems. This ensured the waterproofing was completed swiftly, in excess of 500m2/day, which enabled landscaping finishes to be installed within deadline.The drainage strategy was simplified across all podia through the creation of a horizontal drainage zone above the waterproofing. Axter’s combined reservoir and drainage board was installed, retaining appropriate moisture levels for the specified plant requirements, whilst allowing excess moisture to drain freely away. It also acted as a permanent shutter for concrete works that allowed secondary structures to be built off these areas without contacting the waterproofing system or interrupting the drainage zone.Intensive hard and soft landscaping was completed by Frosts Landscapes Ltd using conveyor technology to distribute the soil and plants across the podia with ease.Systems in useWilotekt®-Plus
Sponsored
The Cheng Yu Tung Building, Jesus College

The Cheng Yu Tung Building, Jesus College

Axter Ltd

Projects of complexity that demand innovative solutions to technically challenging interface design often deliver exceptional buildings. As a shining example, Axter recently completed the roofing systems for The Cheng Yu Tung Building, a landmark project for Jesus College in the heart of Oxford City.Systems in useStarcoat® PMMAForce Dalle®Excel®Cityflor®OverviewThis project required Axter’s extensive range of materials and methods combined to complete the multifaceted interfaces and deliver the demanding architectural design, whilst achieving the project’s ambitious goals.Founded in 1571, and with original buildings from this date, Jesus College is based in the centre of this diverse and historic city. With the development of the Cheng Yu Tung Building the college has undertaken its most significant transformation since the early 18th century.Combining new graduate accommodation, indoor and outdoor communal spaces, state-of-the-art teaching and meeting facilities with the latest digital technologies, this £36m innovative development is intended to have significant impact on the college faculty and students’ learning experience.Axter worked with architects MICA from early in the process, helping to specify solutions that would realise the design vision of lead architect Mandy Franz.“We’d worked with MICA before on a number of projects - including Keble College, University of Oxford - so they knew us and trusted us to add value through being involved with the design,“ comments Axter's Regional Sales Director, Matthew Saunders. “However, this project was a significant step up in complexity, with approximately 18 separate roof areas in total to complete. Looking at the main quad alone there is a raised area, numerous external stairways and walkways to waterproof as well as further raised terraces and inaccessible roof sections. Fortunately, we had significant experience to bring to this challenge.”Sustainability was the client’s major focus from the start, with the college already utilising ground source heat pumps, photovoltaic panels, and a heat recovery and cooling system to ensure zero carbon building operations, as well as reviewing all construction waste to ensure minimum diversion to landfill. We supported this aim working with main contractor BAM Construct UK to carefully plan and schedule the waterproofing systems to be installed, identifying the material composite of each roof to maximise efficacies in installation and logistics.The College’s key priority was to achieve a sustainability-focused design to reduce their carbon footprint. Naturally, this contributed to the challenges of the scheme, such as the additional fire safety requirements in response to the timber-framed construction. To help deliver the College’s ambitions, Axter supported the client’s design team by providing expert knowledge, understanding and application of the current regulations.Tapered roof insulation was used to support energy efficiency and drainage requirements, with bituminous waterproofing throughout. In keeping with the college’s sustainability mission, the main quad features a blue roof system to attenuate rainwater drainage. Other roof areas are finished with wildflower meadows. A combination of exposed and buried waterproofing membranes were consequently required, with additional complexity created by the range of different materials and surfaces involved.“Normally, if our membrane is marrying up to a vertical wall, we would see it come up as a visible detail,” continues Matthew, “but the beautiful Clipsham stonework used for the building façade wasn’t compatible with the typical detailing. We were also challenged by the desired architectural intent to defend the historic aesthetic of the stone, so we created a bespoke solution that has the required guaranteed watertightness whilst also delivering the architectural vision.”Additional challengesThe project started in 2020, just as the UK was trying to navigate the guidelines for operating during the COVID-19 pandemic. Matthew explains: “there were still restrictions in place, such as a general 2-metre distancing requirement, which was challenging in the tighter spaces, for example corridors where you literally couldn’t pass another person. We had an unusually hot summer also, which wasn’t helpful when you have workers in full PPE using 1,400-degree butane torches where use of naked flame was permitted in accordance with NFRC Safe2Torch guidance.”The overall scope of the project, which encompassed multiple terraces at different levels and a mixture of concrete, CLT and steel frame structural composites, was a defining characteristic. “This was a large-scale development to begin with,” adds Matthew. “Furthermore, the university emphasised from the start the centrality of the significant sustainability objectives, and MICA had ambitious solutions in mind in terms of the materials used. Our job was to accommodate these various requests while keeping in mind all of the regulatory and compliance requirements. Achieving those without exception, for a large number of surfaces, does become more challenging where each part of the project has several ambitious aspirations intersecting with one another. Fortunately, we are known for always rising to a challenge.”SolutionsThe pandemic accelerated the shift to a range of technological solutions replacing traditional or face-to-face approaches. Systems were evolved for everything from distancing to digital rather than traditionally signed delivery acceptance.“As a manufacturer, we don’t have to be on site every day,” notes Matthew, “but traditionally we would attend fairly frequently, as well as meeting regularly with partners to agree and then oversee various aspects of the project plan. Fortunately, Axter was already moving towards solutions such as virtual meetings, so we simply shifted much more quickly to those approaches, using them wherever possible.“I think one advantage we have is the breadth of the product range we design. We can offer clients such as Jesus College a full system approach involving multiple solutions, to ensure we use the right system for the right application on each occasion. Our accredited installers are carefully vetted and trained by us, and have worked with us for long enough to know our products inside out.”The range of products we are able to offer, all developed in-house, does testify to the culture of Axter. Comments Matthew: “We are very much a technically-oriented company and that runs through every aspect of our work and our staff. Our sales team are all very aware of the products on that level, they aren’t selling products they don’t fully understand the technical details of. Our long-term partners know that what we offer them is reassurance that, from early-stage design meetings through to completion, whatever challenges they put to us, our response will be considered and robust in terms of quality and compliance.”Systems and products usedExternal stair cores used Axter Starcoat PMMA liquid waterproofing membranes.For the main quad and some lower areas, our innovative Force Dalle warm roof solution was used.Our Excel reinforced waterproofing membranes were used as an exposed membrane finish, with a tapered insulation to ensure the falls and consequent drainage characteristics required by BS 6229.Axter’s Cityflor warm living roof membranes were used as buried applications in several roof terraces, again with tapered insulation.Self-adhesive membranes were used where necessary to ensure compliance with NFRC Safe2Torch Guidelines, especially required due to the timber elements.Acknowledgments"To deliver the increasing demand on a building’s performance specification, combined with the seamless aesthetics of contemporary architectural design, an advanced understanding of technical detailing is required in the design and construction process. The design criteria have also resulted in an extensive range of engineered systems on the market to provide certified, technical solutions for multifaceted interfaces.Working directly with the designers and product manufacturers, we prioritise a full system approach to the weather-tightness of the building, focusing on durability, termination and compliance with current regulations. I have worked with the team at MICA Architects and Axter’s Matthew Saunders on a number of challenging projects, including The Cheng Yu Tung Building, Jesus College, and the HB Allen Centre, Keble College. Matthew Saunders has always been a key consultant for the technical specification of above ground waterproofing systems and the buildings’ thermal performance. He’s an expert in technical detailing and advisor on the materials required to deliver the optimum waterproofing system for the building."Eric O’Hare, Design Manager, BAM Construction www.bam.co.ukWith special thanks to: Tomasz Zozak, who provided the photographs, and BAM Construction Ltd.
Sponsored
The Residence, Nine Elms

The Residence, Nine Elms

Axter Ltd

The Residence required fast, robust hot melt waterproofing that met the demanding construction programme.ChallengesThe fast construction programme on this project imposed stringent requirements with regard to design, delivery, installation sequencing and coordination with Axter’s on site Quality Assurance (QA) team.The rapid build programme meant the waterproofing system needed to be capable of withstanding construction traffic and activity from other trades, with limited protection. Complex roof, elevation and cladding interface construction details resulted in the need for on site bespoke waterproofing detail design change, that maintained guarantees and ensured a defect free construction for the lifetime of the building.Restricted site storage and delivery access combined with the complexities of inner London construction challenged Axter’s logistics team to provide multi-vehicle, timed delivery without risk of delay or programme disruption.SolutionsThrough early involvement in the design process and collaboration with the developer and project architect, it was agreed that Wilotekt-Plus, second generation hot melt structural waterproofing system, was the right solution. The pour and roll application significantly reduced installation times, ensuring all areas were waterproofed quickly in time to receive a variety of roof finishes – living roof, paving, solar panels, etc.Wilotekt-Plus was installed fully bonded to the concrete slab, providing a robust, 7mm thick, self-healing system capable of withstanding significant construction traffic without defect.Upstands were completed using Cityflor root resistant bitumen membranes. Complex details, where a fire risk was identified by Axter QA, were completed using Starcoat QC in accordance with Axter specification requirements and the National Federation of Roofing Contractors (NFRC) Safe2Torch guidelines.Our accredited Axtershield Installer Bracknell Roofing Ltd followed the project specification in full and works were completed to a very high standard. Regular on-site quality checks were conducted by Axter QA personnel to ensure guarantee procedures were followed and programme deadlines were met.AcknowledgmentsAxter is a company with technically advanced products. Every site is quality checked by Axter QA and I receive a clear report. It’s good to have a partner committed to our joint success and capable of dealing with the unexpected.M Gorick - Bracknell Roofing Ltd
Sponsored
Vine Christian Centre

Vine Christian Centre

Axter Ltd

A complete roof refurbishment, including thermal upgrade and full waterproofing of a church centre.Systems in useEcoflex®The project included various roof areas with different systems in situ, all requiring thermal upgrade, and increased falls to remove standing water from the roof. There were also rooflights and roof lanterns that needed to either be replaced or removed and boarded over, a live gas pipe which required lifting to accommodate the new roofing system, and various redundant SVP’s and chimneys.ChallengesThree separate roof areas required upgrading as the existing waterproofing was failing and reaching the end of its service life. Water ingress was occurring, causing damage to the internals of the building.Axter carried out in depth surveys and took various core samples to determine the existing build ups of each roof area. It was identified that remedial works were needed to stop water ingress, thermally upgrade the roof, remove standing water, and remove certain rooflights. Two out of the three areas had redundant and dated rooflights / roof lanterns. There was also an active gas pipe laid across the main roof area which had to be taken into consideration when specifying works.SolutionsThe 3 existing roof build ups included Asphalt with RBM cap sheet and stone chippings, Asphalt with RBM cap sheet and solar reflective paint and finally an EPDM system. Our core samples revealed that the areas with existing asphalt were in good condition. Therefore, Axter advised to only remove the solar reflective paint and the stone chippings to avoid the asphalt from going into landfill and to keep costs down. We used a mixture of torch applied and self-adhered AVCL’s, dependant on the deck type and to comply with SAFE2TORCH areas. Axter’s Ecoflex® ADH single ply membrane was the system of choice as this kept the use of naked flames to a minimum as the building remained in use throughout the refurbishment programme. The system provided a 20 Year Guarantee covering design, materials and workmanship and achieves Broof(T4) fire certification.A live gas pipe was running across the main roof area. It was decided with the client that this would be replaced and raised to accommodate the new roofing system.As this was a live site, the safety of the client and their visitors was a risk that needed to be considered. Risk and method statements were developed and written with the client’s ongoing activities in mind. The contract was carried out without the occurrence of any accidents or incidents.AcknowledgmentsWe were delighted to have Axter and the Nautilus work on our roofing project and again were delighted with the outcomes. From initial consultations with both Nautilus and Axter we found them to be highly knowledgeable and professional in providing solutions and specifications. Axter’s attention to detail manifested through their survey work and their recommendations provided us with a great deal of assurance in the project, along with ongoing technical assistance from the Axter team to provide reassurance at different junctions in the project. Nautilus were extremely professional in their approach and a pleasure to have on site. Their high regard for health and safety and CDM on site was also evident and ensured a safe environment for all stakeholders. The project was completed by Nautilus in a timely manner and certified by Axter, giving us high confidence in the completed works. A real pleasure to work with on all sides.Andy Lee , Vine Christian Centre
Sponsored
West End Gate, London

West End Gate, London

Axter Ltd

Systems in UseWilotekt®-PlusForce®Force Dalle®Aquamodul®OverviewBerkeley Homes initially contacted Axter in early 2017 about their project to create 844 apartments (including 175 affordable units), plus 8 shops, a restaurant, and a public plaza. The development, located in Edgware Road, will bring prosperity and jobs as well as housing, to a part of London in need of regeneration.The development involves 11 apartment blocks and is divided into 4 phases. Axter were involved in design prior to works starting, and were subsequently awarded the contract for Phase 1, later expanded to include Phase 2 and the current Phase 3.This is an update to a project we initially wrote about in its first phase. As noted there, Phase 1 was complicated by the fact that the Government amended the Building Regulations in 2018, after design work was completed and approved, imposing stricter requirements in relation to combustible materials in high-rise buildings. Timing meant that the developer was permitted to proceed under the old regime, but elected to apply stricter safety standards including a voluntary change to the system used on the balconies that was both tested to BRoof(t4) and included non-combustible insulation. The Axter team had to work quickly to amend designs but were able to modify the approved solution so that work could continue as scheduled.Phil Saunders, Regional Sales Director at Axter, has been our lead throughout the work. “This is one of the most challenging projects I have worked on,” he notes, “but also one of the most rewarding. Unique solutions were required to solve more than one problem, but it has been great to work on a development involving many technically elegant and aesthetically pleasing aspects, with a range of roofing systems and finishes, including Blue, Brown and Green Roof elements.”Additional challengesWestminster Council’s planning requirements included specific stormwater attenuation targets. With limited space onsite, Kevin Leahy, Technical Director at Berkeley Homes, was considering a Blue Roof solution, something the developer had not implemented before, so support from a technical manufacturer was especially important from the outset.Numerous other difficulties have had to be overcome during this project. Work was disrupted by Covid lockdowns not long after roofing commenced in 2019. Phases 2 and 3, which were very similar, also required us to support our partner through complex change: Phase 1 involved an inverted roof, a solution assumed to carry forward. However, assessment of weight restrictions and outlet positions meant that design would need to switch to a warm roof with tapered insulation.Additionally, work has continued throughout the period of the Ukraine conflict, where prices and supply of materials have been difficult to navigate.SolutionsTo achieve planning permission, Axter worked with Kevin and Berkeley Homes between 2017 and 2019, presenting the resultant roofing design for approval. We were able to demonstrate that the plans met sustainable drainage obligations. The London Plan for sustainable design and construction also imposed requirements, which were met by a mix of living roof solutions including Green Roof and Brown Roof finishes.“We’re happy to present Westminster Council to support the planning application,” continues Phil. “We have worked with Berkeley Homes many times and continue to do so on several projects. Nothing matters more to us than building and maintaining ongoing relationships with partners who know they can trust us to take weight from their shoulders.”Construction continued throughout the lockdown period, with Axter working hard to ensure uninterrupted supply. Materials continued to be delivered in a safe manner, and QA reviews were held virtually until we could resume our usual regular site visits.A switch in roofing approach generally changes the sequencing of work such as integration of roofing and door thresholds. “We were able to come up with an innovative solution involving multiple systems, including cold-applied liquid waterproofing, that permitted the original sequencing to remain,” says Phil. Change was also required in relation to upstand penetration details and movement joints.Throughout the project, Axter has been able to provide partners with full designs involving bespoke details, plus rainwater and u-value calculations, to ensure compliance at every stage.“We worked hard to find the smartest, most cost-effective solutions,” adds Phil. “We also appreciated that this was not the time to be too rigid in pricing. Some pain all round might be unavoidable in this difficult period, but we aimed to share the impact. We were also able to offer partners a guarantee of price stability for a set period of time, so they could proceed with certainty.”Axter manufactures its own systems and works carefully to plan ahead and liaise with long-standing supply partners. This allows us to stay ahead of shortages and offer accurate delivery timelines. Company-wide, we have been able to supply all systems as pledged.All of Axter’s approved installers must complete training specific to the systems involved, but in this case so many bespoke design elements were involved that we organised training specific to the project for all operatives. This training was also extended to the Berkeley Homes construction team, to ensure they were supported in how the roofing would integrate with other areas of construction.“This has been an exceptionally successful project”, comments Phil. “Hurdles have arisen, but with communication and hard work we have supported our client through rapid transitions and financial challenges. We have been very flexible on pricing, but we were not necessarily the cheapest initial bid. We were chosen anyway, because I think Berkeley Homes understands we add value that makes us the cost-effective option for the building’s future lifetime.”Phase 3 designs were approved early this year, with work just starting. Axter is now busy with design for Phase 4, with the project expected to continue through to 2025.

Showing 1-28 of 28